The Standard Waterfall Model for Systems Development
COLLECTED BY
Organization:
Alexa Crawls
Starting in 1996,
Alexa Internet
has been donating their crawl data to the Internet Archive. Flowing in every day, these data are added to the
Wayback Machine
after an embargo period.
this data is currently not publicly accessible.
The Wayback Machine - https://web.archive.org/web/20040403211247/http://asd-www.larc.nasa.gov:80/barkstrom/public/The_Standard_Waterfall_Model_For_Systems_Development.htm
The Standard Waterfall Model for Systems
Development
The standard waterfall model for systems development is an
approach that goes through the following steps:
- Document System Concept
- Identify System Requirements and Analyze Them
- Break the System into Pieces (Architectural Design)
- Design Each Piece (Detailed Design)
- Code the System Components and Test Them Individually
(Coding, Debugging, and Unit Testing)
- Integrate the Pieces and Test the System (System Testing)
- Deploy the System and Operate It
This model is widely used on large government systems,
particularly by the Department of Defense (DOD).
As part of this standard approach, the party responsible for
contracting out the system development (ESDIS for the ECS
Contract) can call on a number of tools to help plan and document
the system. ECS followed this planning approach, which means that
early in the system development, ESDIS set up a
standard
set of documents
for the contractor to supply, as well as a
contractual schedule for the major pieces. The development
process provided a number of design reviews, notably
- Conceptual Design Review
- Requirements Review
- Preliminary Design Review (PDR)
- Critical Design Review (CDR)
Until these reviews were completed, there would be little code
developed. After the CDR, the contractor would code to the
design.
The standard reference for estimating the cost of the system
is the COnstructive COst MOdel (COCOMO) developed by Dr. Barry
Boehm while he was at TRW [Boehm, B., 1981:
Software
Engineering Economics
, Prentice-Hall]. This model relates
the development time and workforce [man-months] to the
"Source Lines of Code" (SLOC). Roughly, for an ECS type
of system ECS, the workforce (and therefore cost) scales as the
cube of the development time. There are simple versions of the
model and much more complex ones. Generally, all of the
relationships used to predict these relationships are statistical
in nature: Dr. Boehm and other workers in software project cost
estimation build a database of project schedules and costs and
then regress those against SLOC estimates. The most recent
version of Dr. Boehm's work is provided in [Boehm, B., et al.,
2000:
Software Cost Estimation with COCOMO II
,
Prentice-Hall.].
There have been a number of criticisms of the standard
waterfall model, including
- Problems are not discovered until system testing.
- Requirements must be fixed before the system is designed
- requirements evolution makes the development method
unstable.
- Design and code work often turn up requirements
inconsistencies, missing system components, and
unexpected development needs.
- System performance cannot be tested until the system is
almost coded; undercapacity may be difficult to correct.
The standard waterfall model is associated with the failure or
cancellation of a number of large systems. It can also be very
expensive. As a result, the software development community has
experimented with a number of alternative approaches, including
- Spiral Design (Go through waterfalls, starting with a
very rough notion of the system and becoming more
detailed over time)
- Modified Waterfalls (Waterfalls with Overlapping Phases;
Waterfall with Subprojects)
- Evolutionary Prototyping (Start with initial concept,
design and implement an initial prototype, iterate as
needed through prototype refinement until acceptable,
complete and release the acceptable prototype)
- Staged Delivery (Go through Concept, Requirements
Analysis, and Architectural Design - then implement the
pieces, showing them to the customer as the components
are completed - and go back to the previous steps if
needed)
- Evolutionary Delivery (a cross between Evolutionary
Prototyping and Staged Delivery)
These are discussed in considerable detail in [McConnell, S.,
1996:
Rapid Development, Taming Wild Software Schedules
,
Microsoft Press]. Commercial software projects often reduce the
formality of the full waterfall model. In the last few years, a
paradigm known as eXtreme Programming has emerged that emphasizes
reducing the cost of software changes, developing test cases
before coding, developing code using pairs of programmers, and
putting most of the documentation into the code [Beck, K., 2000:
Extreme
Programming Explained, Embrace Change
, Addison-Wesley].